Faster and more material-efficient bridge construction with thin-walled structural precast elements

The Technical University of Vienna (TU Wien) has developed a new construction method for the fast and material-efficient construction of post-tensioned concrete bridges. The development of the LT bridge construction method drew on experience gained with the construction of bridges with thin-walled precast girders erected over the Lahnbach and Lafnitz Rivers and with the first application of the balanced lowering method. An LT bridge consists of thin-walled longitudinal girders with box cross-sections, deck slab elements arranged on the longitudinal girders, and a layer of concrete cast on top of the deck slab elements and the longitudinal girders. The concrete topping and the starter bars connect the longitudinal girders to the deck slab elements.

Fig. 1 is a simplified representation of the LT bridge construction method, which is especially suited for the construction of post-tensioned multi-span bridges. Fig. 1 shows a configuration during the construction of a bridge section. The post-tensioned precast girders are arranged in the longitudinal (L) direction. The deck slab elements are installed on the longitudinal girders in the transverse (T) direction. Fig. 1 shows a configuration where four of six deck slab elements are placed. The entire transverse reinforcement, the stirrup reinforcement, and the lower longitudinal reinforcement have previously been installed in the precast plant. Utilization of the precast elements and minimization
of the reinforcing steel installed at the construction site enables the construction of sections with a span of 25–60 m in weekly cycles.

Construction of the first LT bridge took place in 2022 as contracted by ÖBB Infrastruktur AG. Constructing the superstructure of a single-span frame bridge in three and a half days was possible. 40 % of the concrete mass required in the initial planning was saved. In January of 2023, ÖBB Infrastruktur AG commissioned the planning of an
additional bridge using the LT bridge construction method.

x

Related articles:

Issue 08/2013 Research project of TU Vienna

Thin-walled precast concrete girders for bridge construction and civil engineering

In building and industrial construction, lattice-girder floor slabs and double-wall elements have been successfully used for years. These semi-precast elements of 5-7cm thickness serve as permanent...

more
Issue 04/2019 TECNOCOM/PROGRESS GROUP

Tecnocom molds form bridge girders at Nawaseeb Road

Infrastructural projects in Kuwait are still in the focus of local governmental-backed investments. In order to improve connectivity regionally and globally projects in this sector are viewed as a...

more
Issue 02/2014 From building component to engineering component

Bridge girders made of double walls erected by balanced lift method –

Motivation New bridge structures must be erected as quickly as possible to maintain the existing traffic network or, in the case of overpass structures, so as not to interfere with the traffic below...

more
Issue 02/2017 Potentials for the precast industry

Bridge construction with UHPFRC precast elements

Stringent requirements for bridge structures due to rising traffic volumes, accompanied by the age structure of bridges in Germany, are calling for fast construction of new and replacement structures....

more
Issue 12/2020 ZEMENT+BETON

Global innovation in bridge construction

With the type of „folding bridge“ developed at TU Wien another Austrian innovation does exist that saves costs and time in the implementation of infrastructure projects. Two bridges are being...

more