Magnetic formwork component for circulation plant in Chile

According to the forecasts, the Chilean construction sector has left the bad times behind. Experts estimate growth of one to three percent in 2018. On account of its volume and the high number of employees due to high work intensity, the construction industry is a relevant economic sector in Chile. In addition, Chile has one of the highest per capita incomes in South America – a further factor that is stimulating the construction industry to invest in efficiency-increasing building and construction methods.

Ratec scores at Baumax

Baumax, a Chilean consortium of various specialists, took a decisive step towards the future in 2017 with the start-up of its automated circulation plant for the manufacture of steel reinforced concrete elements for residential and industrial construction. The production facility is the first automated circulation plant for the manufacture of precast concrete elements in Chile.

The shuttering solution for the modern precast plant was developed and supplied by Ratec. The particular challenges for the shuttering concept were firstly to tailor it to suit the automation and secondly to make a suitable proposal for the partly complex details of the construction system developed by the customer.

Development of a robot-compatible shuttering

The use of wire rope loops was foreseen for the connection of the elements. For economic reasons the customer wanted to have an alternative to conventional wire rope loop boxes. To solve this, Ratec developed robot-compatible shuttering with integrated wire rope loops as well as grouting groove profiles for positioning on the shuttering or pallet, to which single wire rope loop boxes can be individually attached.

In the case of shuttering with integrated wire rope loops, the latter are held in place in the shuttering profile by a PE insert. The PE holder can be pulled out of the shuttering for stripping, subsequently removed from the loop and reused for the next concreting procedure.

In order to implement corner joints in the element, a magnetic grouting groove profile was developed for placement on the pallet or shuttering along with a matched positive-locking magnetic box with integrated loop for setting on the grouting groove profile. These magnetic boxes can also be removed after concreting and reused. Only the wire rope loop remains in the element.

The prerequisite for the implementation of this solution was the static approval for the connection solution described by the competent building authority, which was confirmed in the specific project. The shuttering was virtually refinanced due to the saving of costs using the wire rope loop connections. Usability in other projects is ensured in the case of static approval by the respective regional authorities.

Central and South America: markets with potential

Precast concrete construction, the use of robot-assisted plants and planning software are trending topics in Chilean construction sector (source: GTAI). Also in other Central and South American construction industries, the demand is growing for such solutions. In Peru, there is a very high demand for affordable and earthquake-proof living space, accompanied by government housing building programmes, driven by a strengthened middle class and attractive credit conditions for house buyers.

Similarly in Panama, one of the region’s fastest growing economies: here the industry drivers are above all infrastructure projects, but strong investments are also being made into residential construction.

x

Related articles:

Issue 08/2020 PHILIPP GRUPPE

A transport anchor of a somewhat different kind – the new wire-rope lifting box

Innovations in transport anchor systems are rather rare, because such systems with threaded sleeves or spherical balls – e.g., as hole anchor systems or wire-rope lifting loops – have been long...

more
Issue 03/2010

Ratec GmbH · Hall B1, booth 320

The Ratec company with production facilities in Hockenheim (Germany) and Clearwater (Florida) is famous for its leading position in the development of magnet-based shuttering technology. The product...

more
Issue 02/2020 PHILIPP GRUPPE

Simple design and more power for rope loop connections

The company Philipp has recently expanded its Power Series of approved products for connecting precast reinforced-concrete elements with flexible rope loops by introducing two connection rails at the...

more
Issue 03/2012

Abus adds on: 120-ton wire rope hoist available

The overhead crane and hoist manufacturer Abus Kransysteme GmbH is expanding its product range. As of now, the product portfolio of the Gummersbach-based company includes a double-rail hoist trolley...

more
Issue 06/2010 New product to connect wall elements

Peikko launches single wire connection loop

Peikko’s patented PVL-product has national approval for static loads and has gone through a rigorous testing program at the VTT Technical Research Institute of Finland. The product becomes available...

more