Eirich

Mixing technology for a new railway sleepers plant

Leonhard Moll Betonwerke GmbH & Co KG, from Munich, is a leading manufacturer of prestressed rail and switch sleepers for the rail network of the German Deutsche Bahn railway system and has a production capacity in Germany of over one million tons of prestressed concrete sleepers each year. Eirich mixing technology is already in use at a number of sites. Now a complete new production plant at the Biebesheim site has been built, for which Leonhard Moll once again chose mixing technology from Eirich.

The purpose of sleepers is to support the rails and to transfer the pressure of the axle loads to the substructure via the foundations. Originally made of timber or steel, since the middle of the last century they have been replaced by sleepers made of reinforced concrete instead. Some of the reasons for this were: The fact that the much higher weight provides a firmer and more stable track position, resulting in reduced maintenance costs. The rolling resistance of the trains is lower, track buckling due to thermal stress is reduced and the there is less running noise than with timber or steel sleepers.

The replacement of old sleepers as well as the construction of new lines and overhaul of existing ones means that there is a constant demand for new concrete sleepers. These sleepers have to comply with strict requirements in terms of quality. As a consequence, the concrete which is used requires optimum preparation.

 

Further development of the ring-trough and planetary mixer

The new production plant uses the early stripping process, meaning that it uses relatively dry mixes. Conventional mixing systems are mostly inadequate to cope with this. When it comes to slightly damp and dry concrete in particular, the strengths of Eirich mixing technology really come into their own. As a further development of the ring-trough and planetary mixer, the design of the system makes it possible to achieve higher tool speeds which means that a maximum of shear forces can be introduced into the mix. This achieves a better distribution of cement and moisture and more homogeneous fresh concrete. In turn, this ensures that the concrete is very uniform when inserted into the mould, with greater stability in stripping immediately afterwards.

The order placed with Eirich was for a complete mixing system with flat feeder and twin-belt elevators, raw material silos for six aggregates and three types of cement, steel structure for two independent mixing lines with Eirich type RV19 intensive mixers with a capacity of 1,500 liters and an Eirich machine control system. With the exception of the infeed, the entire system was integrated in the customer-provided production building and is “invisible” from the outside. Due to problematic groundwater conditions, the system concept involves no deep foundations, i.e. there was no need for a hopper pit.

 

Excellent working relationship

Both partners have emphasized that the working relationship was excellent before and during the construction phase. “What was important for us in terms of the choice of supplier for the mixing system were, along with compliance with the requirements with respect to the quality of the concrete, naturally the short mixing times made possible by these high-performance mixers, but also the working relationship with a partner with which we have already had nothing but positive experience,” says Pierre Paulin, Technical Director at Leonhard Moll. This is added to by Uwe Schnitzler, Head of Mechanical Engineering at Eirich: “What was particularly agreeable was the pragmatic solution-oriented teamwork at project manager level, which ultimately led to the punctual commissioning and hand-over of the system to Leonhard Moll.”

At the new Biebesheim plant Leonhard Moll will be able to produce up to 400,000 sleepers a year in the first phase of construction. Production started in autumn 2017 and has been running highly satisfactorily since then.

x

Related articles:

Issue 04/2019

New system engineering technology for railway sleepers curing

The company Leonhard Moll Betonwerke GmbH & Co KG has a long tradition going back as far as to 1929, when the Munich building contractor Leonhard Moll founded a concrete plant. The foundation stone...

more
Issue 11/2019 TEICHMANN KRANE

Two gantry cranes for L. Moll concrete sleeper plant

Teichmann Krane has supplied Leonhard Moll Betonwerke GmbH & Co. KG located in Biebesheim with a 2 x 10 tons gantry crane with a span of 42 m within only 4.5 month. The crane is used for the transport...

more
Issue 04/2021 REA JET

Type features on concrete sleepers defy wind and weather

In front of the concrete sleeper factory of Leonard Moll Betonwerke GmbH & Co. KG located in Biebesheim, two cranes having a span of 42 m and a load capacity of 20 tons are moving railway sleeper...

more
Issue 01/2018 Weckenmann Anlagentechnik

Modern plant equipment for production of prestressed concrete railway sleepers

Since their introduction in 1970, the type B70 sleeper is the mostly used prestressed concrete sleeper in the rail network of Deutsche Bahn. The sleeper can be used flexibly, has a load-bearing...

more
Issue 08/2022 KRAUSKOPF MASCHINENTECHNIK

Reconditioning versus replacement with new mixer wearing parts

Sustainable action, apart from climate change and digital transformation, is seen as one of the greatest challenges of our time. The definition of sustainability in this context is by no means so...

more