Fire and flame: New Kirchdorfer managing director fires up the heater at the cement plant
03.03.2025
Figure: Kirchdorfer Gruppe
After a six-week overhaul, the rotary kiln at the Kirchdorf cement plant is back in operation.
A total of 29,000 working hours were invested. Important work included the replacement of 230 tonnes of refractory material and 1,320 filter bags. This regular maintenance work is crucial for the smooth operation of the plant.
New Managing Director Joao Paulo Pereira fired up the furnace for the first time. At his side were long-serving employees Erich Stadler (37 years of service) and Franz Lueger (47 years of service), who started up the furnace for the last time before their retirement.
In addition to the routine work, numerous modernisations were carried out, including a new dosing system for substitute fuels, the renewal of screw conveyors and a new storage tank.
With an annual capacity of around 500,000 tonnes of cement, Kirchdorfer Zementwerk, the parent company of the Kirchdorfer Group, is consolidating its position as an innovative and forward-looking employer in the region.
CONTACT
Kirchdorfer Gruppe
Kirchdorfer Platz 1
2752 Wöllersdorf/Austria
+43 5 7715 100 0