Balanced-lift method for prestressed concrete bridges – 25 % lower cost compared to steel-concrete composite bridges

The first-time application of the balanced-lift method for the bridges
over the Lahnbach and Lafnitz rivers in Austria proved that these prestressed concrete bridges with 2.0 m high bridge girders
constructed according to this method incurred 25 % lower costs compared to the originally planned steel-concrete composite bridges with 4.2 m high steel girders. Costs could be reduced not only as a result of applying the balanced-lift method, but also by installing thin-walled, trough-shaped precast girders composed
of 70 mm thick precast slabs for the side walls and 120 mm thick bottom slabs. Tendons were incorporated in order to compress
the 20 mm thick joints between the precast slabs in the final
condition. Two 36 m long bridge girders were assembled in a vertical position for each of the bridge girders. Compression
struts were required for rotating the bridge girders from their initial vertical position into their final horizontal position. In the installed condition, these struts are part of the bridge structure and reduce its spans. After filling the compression struts and the thin-walled precast girders with in-situ concrete and completing the deck slab, the two bridges exhibit the same performance characteristics as conventional prestressed concrete bridges, providing the added benefit of a dense and visually appealing fair-faced concrete surface.

The balanced-lift method is also suitable for erecting replacement structures because it provides the option of installing the compression
struts and the bridge girders in the vertical position in confined environments. The use of precast elements for the compression struts and the bridge girders comes with the advantage of a short time to project completion because no formwork or shoring system is needed on the construction site.

x

Related articles:

Issue 02/2014 From building component to engineering component

Bridge girders made of double walls erected by balanced lift method –

Motivation New bridge structures must be erected as quickly as possible to maintain the existing traffic network or, in the case of overpass structures, so as not to interfere with the traffic below...

more
Issue 12/2020 ZEMENT+BETON

Global innovation in bridge construction

With the type of „folding bridge“ developed at TU Wien another Austrian innovation does exist that saves costs and time in the implementation of infrastructure projects. Two bridges are being...

more
Issue 07/2016 Haitsma Beton

Longest box girders delivered to bridge project at Zuidhorn

To relieve the lift bridge across Van Starkenborgh Canal in Zuidhorn, Netherlands, of some of its load and to remove traffic congestion, municipal authorities designed a new, 152 m long bridge with...

more
Issue 08/2013 Research project of TU Vienna

Thin-walled precast concrete girders for bridge construction and civil engineering

In building and industrial construction, lattice-girder floor slabs and double-wall elements have been successfully used for years. These semi-precast elements of 5-7cm thickness serve as permanent...

more
Issue 06/2023

Faster and more material-efficient bridge construction with thin-walled structural precast elements

The Technical University of Vienna (TU Wien) has developed a new construction method for the fast and material-efficient construction of post-tensioned concrete bridges. The development of the LT...

more