Wenker gantry crane modernized in record-breaking seven weeks

The Wenker gantry crane getting on in years with a load capacity of 35 tons and a span of 2 x 12 tons used by a Hessian construction company, the Faber & Schnepp Hoch- und Tiefbau GmbH & Co. KG, was to be modernized completely.

At first, the gantry crane (year of construction 1971) was dismounted on its place of origin in Langgöns, Hesse, then being transported to the production halls of Teichmann Krane in the city of Essen for overhauling and retrofitting. Owing to the extensive retrofitting measures planned including an increase of the load capacity and for not disturbing the ongoing operations of the customer, reconstruction on site was not possible. At the location in Essen, the steel construction and the supports of the gantry crane were overhauled completely, including partial sand-blasting and mechanical rust removal, and subsequently applied with a new coating.

 

Turn old into new

In parallel, the present reach of the crane was extended by 2.7 m and the load capacity was increased from the former 2 x 12 tons to 2 x 16 tons now. In addition, the entire electrics of the crane, including the wiring and the trailing cable installation, were renewed, and the existing control system was converted to a PLC control with integrated remote maintenance module. The crane was provided with new switchboards and new LED lighting. Moreover, two new trolleys as well as a new crane drive system were engineered and manufactured at the location of Teichmann Krane in Essen.

It took only seven weeks from the disassembly up to the reassembly and commissioning of the crane.

CONTACT

Teichmann Gruppe

Am Stadthafen 40

45356 Essen/Germany

+49 201 834 55-74

www.teichmanngruppe.de

x

Related articles:

Issue 12/2020 TEICHMANN KRANE

New gantry crane for Dutch precaster

Teichmann Krane delivered a new gantry crane with an 8-ton carrying capacity and a span of 29 m to the production site of the precaster VBI Schuilenburg in Oostermer in the Netherlands. In the future,...

more
Issue 01/2014 Stahl CraneSystems

Stacker crane for handling precast concrete parts

In the lead-up to its 50th anniversary, the Bavarian company Lindermayr modernized, in 2012, its production plant for floor plates for floor systems and double walls, initially commissioned in 1991....

more
Issue 11/2019 TEICHMANN KRANE

Two gantry cranes for L. Moll concrete sleeper plant

Teichmann Krane has supplied Leonhard Moll Betonwerke GmbH & Co. KG located in Biebesheim with a 2 x 10 tons gantry crane with a span of 42 m within only 4.5 month. The crane is used for the transport...

more
Issue 11/2017 Kranbau Köthen

New gantry crane for handling of concrete elements

Only ten months after awarding a contract, the new lattice gantry crane is already operating at the storage area of company Kemmler. The crane supplier Kranbau Köthen developed a customized crane...

more
Issue 07/2019 TEICHMANN KRANE

100 t gantry crane delivered to Haba-Beton within just six months

Teichmann Krane set a new record in terms of delivery time by supplying a 100?t double-girder gantry crane to Haba-Beton in Mantel, Germany, within just six months. This 25?m span gantry crane will be...

more