High-tech solutions in wall and floor production

Automated production of multi-layer precast elements

 Sommer Anlagentechnik GmbH and SAA Engineering GmbH have jointly developed a new, automated process for the manufacture of sandwich walls, insulated double walls, and solid walls and floors.

This solution opens up new areas of application in the manufacture of complex precast components whilst providing highest flexibility and productivity when producing multi-layer precast elements. The process called JFI (Joint-Facing Insulation) includes three automated production steps:

1. Production step for applying a joint sealing compound (Joint-Design Filling Robot, JDFR)

In this step, a joint compound is automatically applied to the surface of the production pallet in a grid pattern according to the CAD plans. This sealing compound provides the following features: it replicates the contours of the joint, does not link to the joint concrete, equalizes the tolerances of the production pallet, dampens vibration and thus protects facade panels from damage during the subsequent compaction process, keeps the facade panels firmly in their positions, and enables sealing and leveling to the formwork edges.

2. Production step to automatically convey facade facing elements (tiles, clinker bricks etc) to a transport and cutting unit and place them accurately on the production pallet using a robot (Facing-Stone Placing Robot, FSPR)

A robot removes tiles, clinker bricks etc from the transport unit and conveys them to a cutting unit or to the placing robot. The placing robot grabs each piece, moves it into its defined position and accurately presses it into the previously applied joint compound at a spacing that can be freely defined (on the basis of CAD data).

3. Production step enabling automated feed, cutting, drilling and application of the insulation layer, and automated placement of wall connectors (Insulation Process Application Robot, IPAR).

To date, both insulation layer and wall connectors have always been placed manually: the insulation panel was cut to size, wall connector openings were drilled, the insulation panel was placed on the fresh concrete, the wall connectors were inserted and fixed, and joints were filled with foam. However, this manual production process required a high amount of labor at the precast plant and was thus not associated with significant benefits compared to insulating the element on the construction site. The manual method makes it impossible to complete work within the cycle time of the pallet circulation system. The new, automated process is different: the insulation panels delivered in stacks are automatically destacked and cut to size using CAD data. Boreholes or openings are inserted to accommodate the wall connectors. A placing robot positions the panels on the freshly cast face concrete layer and places the wall connectors in the previously made openings in the fresh concrete in a fully automated process. This system is suitable for the manufacture of all types of insulated precast elements (floors, double walls, sandwich walls).

Sommer Anlagentechnik GmbH, based in Altheim/Landshut, Germany, is responsible for design and engineering, electrical systems planning, the manufacture of control cabinets, and the production of the new systems. SAA Engineering GmbH supplies the equipment control systems – a demanding task for the Vienna-based system automation experts: in the first step, the CAD system specifications had to be analyzed, and the interfaces were extended because the number of elements to be produced clearly exceeds the capacity provided by the usual „UNI“ interfaces. At the same time, a seamless representation in the BIM (Building Information Model) was ensured. Data processing in the master computer was optimized, and new machine interfaces were developed to enable NC data interchange and process data feedback. Moreover, control systems for the articulated robots had to be developed for all work stations on the basis of the tried and tested MFSR robot control and visualization system.

In the meantime, the new, automated production line has successfully completed its testing phase and attracted first buyers. The new system will be presented to a broader audience for the first time on 6 and 7 December 2011 on the occasion of the „Engineering Days“ to be held in Vienna.


x

Related articles:

Issue 04/2013 Sommer Anlagentechnik GmbH

JFI process nominated for Innovation Prize

The JFI process is an innovation from Sommer Anlagentechnik and SAA Engineering, which has been patented in 2012. The process enables fully automated production of multi-layer concrete elements to...

more
Issue 06/2016 Greencode

Multifunctional ­insulation wall

The innovative Greencode insulation wall unit makes it possible to benefit from an industrial production environment as early as at the shell construction stage. Each wall unit is designed...

more
Issue 10/2016

Bachl strengthens precast division with new double-wall production

Continuity and innovation are the two basic principles that characterize the tradition of Karl Bachl GmbH & Co. KG, in the Lower Bavarian city of Röhrnbach. The family enterprise, founded in 1926 as...

more
Issue 03/2019 ANKOX

Polyfleece SX 1000 Wall – Precast concrete elements with integrated surface sealing

The advantages of sealing surfaces with the fresh concrete composite system Polyfleece SX 1000 Wall, which has been registered for patent approval, can now be used also in the precast concrete sector....

more
Issue 05/2012

Sustainable construction with thermal walls

Thermal walls with integrated core insulation make a decisive contribution to energy savings. Therefore, they are especially qualified for being used as building material if the building owner or the...

more