Planning, manufacture and erection of precast elements

Hammacherstrasse bridge over motorway BAB 46
in Hagen, Germany

The first modular bridge in the German state of North-Rhine/-Westphalia (NRW) was erected in 2016 as the result of an idea competition of the NRW Ministry of Transport and the Chamber of Construction Engineers “Bau” conducted for speeding up bridge construction sites and for reducing traffic closure. SWECO GmbH had won this competition with an integral composite steel frame construction.

HEITKAMP Brückenbau GmbH was awarded the contract as general contractor, and OTTO QUAST Fertigbau Lindenberg GmbH & Co.KG was commissioned to manufacture the precast elements required for the project.

The bridge has an overall total length of 42.80 m, a width of  11.60 m and passes over motorway BAB 46 near Hagen. It is composed of approx. 180 precast elements with individual weights of up to 62 tons, which were required to be manufactured ând assembled to high precision specifications.

Construction took place from April to August 2018 over 100 calendar days, with the motorway partially closed to traffic on only three weekends. Traffic on the A46 was only minimally impeded: two lanes were at all times available in each direction of traffic.

The bridge foundations, embedded on vibrated stone columns with ballast, each consist of seven individual foundations for every bridge abutment side. These were glued together and tensioned. Due to the 28 GEWI connecting bars in the foundation, which were required to fit in their installed position into the abutments resting above, very special measures were required here to ensure dimensional accuracy.

The two abutments of the bridge consisted of four individual members on the north side and six on the south side. The very high reinforcement percentage of the highly complex embedded parts presented a special challenge. In order to ensure that the concrete fully encases the above embedded parts, the upper four abutments were required to be manufactured upside down and afterwards inverted by three cranes.

The 14 bridge decks were subject to very narrow tolerances and weighed 46 t each; they were provided with a large number of heavy embedded parts (up to five tons each).

Trials conducted on this construction method have shown that it can considerably reduce construction time at the site and should be used more widely in the future.

x

Related articles:

Issue 09/2018 OTTO QUAST/STRASSEN NRW

First fully prefabricated motorway bridge built in NRW, Germany

Following what could be termed a record-breaking short construction time of only 100 days, the new Hammacher Strasse bridge in Hagen in the German federal state of North Rhine-Westphalia, spanning...

more
Issue 02/2017 Precast elements in bridge construction

Opportunities and methods to accelerate the construction­ process

Maintaining federal highways in good condition is one of the primary objectives to ensure the mobility that Germany requires in the long term to retain its attractiveness for businesses. Bridges are...

more
Issue 03/2021 KLEIHUES BETONBAUTEILE

Faster construction with precast elements – Railway bridge near Steinfurt

The rehabilitation of railway bridges is generally focusing on one central objective: In order to reduce disruptions of the rail traffic to a minimum, the line closures, during which the rail traffic...

more
Issue 02/2020 Modular concrete construction

Development of an innovative modular bridge

In Germany, modular bridge construction methods have so far been applied only to a limited extent compared to other European countries or North America. However, public road authorities are...

more
Issue 02/2017 Potentials for the precast industry

Bridge construction with UHPFRC precast elements

Stringent requirements for bridge structures due to rising traffic volumes, accompanied by the age structure of bridges in Germany, are calling for fast construction of new and replacement structures....

more