Precast elements for stadiums and convention centers
Reconstruction of the East and West Stand of Weser Stadium, Bremen, Germany (conversion of existing structure)
West Stand construction time: mid-May to December 2009
East Stand construction time: mid-May to December 2010
Scope of construction activities: technical design, production and assembly of 583 lower and upper tier elements, 30 stepped beams, 22 joists, 48 stair elements and 875 steps
Contractor: Kamü Bau GmbH
Client: Bremer Weserstadion AG
General planner: ProCon Ingenieurgesellschaft für wirtschaftliches Bauen mbH
Architect: Wabe-Plan
This project was to convert a former multi-purpose...