Challenge, loadbearing architectural concrete façade “New Chancellor Square” Bonn

Buildings

During a period of three years, after cornerstone laying (in 2019), three new buildings
were erected in the heart of Bonn, Germany, where the Bonn Center formerly stood. A 23-story high-rise building with a curtain wall and two six-story buildings were executed with a loadbearing façade in architectural concrete. Each ground plan resembles a pentagon with inner courtyard. This presentation focusses exclusively on the execution of buildings 2 and 3, the loadbearing façade of which was executed by the Zech-owned precast plant BWE-Bau Fertigteilwerk GmbH.

Loadbearing architectural concrete façade

The special feature of the building is the loadbearing façade and the geometry of the architectural precast concrete elements. The load transfer for the building, except for the façade, takes place only by means of the stiffening concrete cores (staircases, diaphragm walls and reinforced-concrete columns) inside the building. The spans of the floors from the concrete cores to the load bearing façade is 7.50 m, creating largely column-free office rooms. The precast elements measure as a rule 5.47 m in width and 3.70 m in height. The floors are connected to the precast elements by special ISO baskets. The façade consists of an assembled precast post-and-beam construction with concrete class C50/60. The concrete optics is white. The surface was processed by acidification, resulting in a uniform and homogenous architectural concrete surface. To protect the precast elements, partial areas were coated with anti-graffiti protection and/or impregnation in the plant.

Structural and planning challenge

This unique construction posed challenges in many respects – of which the structural design of the building is one example. In this situation, there was no system solution for transmitting the load of the floors into the façade – which are excessively heavy to allow an existing standard solution. Moreover, for design purposes, it was necessary to consider the thermal separation and the thermal stress of Δ t = 60° C, associated with a change in length of approx. 2.5 cm in height. An additional challenge arose from the creation of a structure for the cantilevered area suitable for prefabrication. These are just some of the many different details that had to be taken into consideration in planning and implementing this construction project.

This presentation illustrates how the challenges were jointly met in practice and how effective interaction between engineering consultancy and the implementing precast plant for special structures can successfully solve such challenges.

And the question of whether such a façade is still in keeping with the times is also discussed in the presentation.

x

Related articles:

Issue 02/2014 Ohlingsmühle office building in Wuppertal

Load-bearing architectural concrete façade –

A new office and commercial building was constructed directly adjacent to the Ohligsmühle suspended railway station in the city center of Wuppertal. Its concrete façade has a load-bearing function....

more
Issue 03/2013 Ed. Züblin AG

Façade with a load-bearing function

Previously, any attempt at merging the design aspect of a façade with a load-bearing function was subject to tight constraints but state-of-the-art precast technologies enable new options in this...

more
Issue 02/2021

Neuer Kanzlerplatz project in Bonn – Structural challenges and solutions for the façade

“Off-the-shelf” solutions are no longer possible when combining a sophisticated, unique architectural design with a load-bearing architectural concrete façade system. What is required, though, is a...

more
Issue 08/2021

Precast cornices fastened to load-bearing thermal insulation elements

Right in the heart of the city of Heilbronn, adjacent to the Stadtpark, a luxury 4-star plus hotel was built featuring an innovative concrete façade. The design developed by Berthold Architekten BDA,...

more
Issue 02/2020 August Kühne Building in Bremen

Complex building situations shown on an stapeled architectural concrete façade

Building In 2018/19, a new office building was constructed at the original headquarters of the Kühne + Nagel logistics group in Bremen. Its predecessor completed in the 1960s was demolished because...

more